The maintenance queue was a record of what had not been done.

A steel meltshop and caster.

Results at a glance

350 to 178

Open work orders in the maintenance system, down in 2 weeks.

140 to 90

Minutes for a taphole change, 36% better.

42 to 37 hours

To realign the furnace, 12% better, worth about $279K a year in production value.

A heavy brass furnace vessel tilted toward a tapping spout above a waiting ladle, its left flank scarred and rust orange and its right clean brass with a teal glow at the taphole, a neat rack of brass tools standing ready.

The situation

Work orders went in and stayed in, so the queue was not a plan for the week. The hours the caster spent down had never been priced.

What we did

We measured first: a backlog of 350 work orders, technician productivity at 44%, a taphole change at 140 minutes and a furnace realign at 42 hours. Then we priced the downtime, quantifying $230K of casting downtime so breakout prevention, keeping liquid steel from breaking out of the strand in the caster, could be argued in money instead of opinion. The maintenance system became where the backlog was measured and worked down, with tiered huddles and Leader Standard Work putting it in front of the plant’s own managers.

The result

Every figure, and how it was confirmed.

350 to 178

Open work orders in the maintenance system, down in 2 weeks.

140 to 90

Minutes for a taphole change, 36% better.

42 to 37 hours

To realign the furnace, 12% better, worth about $279K a year in production value.

$39K

grade loss prevented. Downtime in February was reported as a record at 4%.

As reported by the principal

How we report value

Next step

If this company sounds like yours, ask us what a discovery would look at in your numbers.

You do not have to be ready to buy anything. One of the three of us will answer the question ourselves.

Ask the principals a question