Automotive stamping7 week program, 2024
Automotive stamping plant: die changeover 89 to 46 minutes in a 7 week program
- 66 changeover observations timed on the floor, which is what the standard was built and corrected from.
- 300 plus feet of forklift travel taken out of every die move.
- Throughput
- Operating system
As reported by the principal
Read the case study